Elwha Nearshore Rising: Beach Lake Shoreline Restoration

Why Did This Shoreline Need to Be Restored ?

Over 100 years ago, before the Elwha River dams were built, the Beach Lake area of the Elwha shoreline along the Strait of Juan de Fuca wasn’t even a lake -it was a part of the river estuary.1908 aerial

Above, you can see in a 1908 map that the Elwha River had an almost mile long tidal lagoon complex that was connected to the river and was protected by a sand spit.  These back spit lagoons are critical for resting juvenile salmon, including Chinook, coho, chum, steelhead, and bulltrout, as well as forage fish. Over the course of the next century, the installation and operation of two dams in this watershed severely decreased delivery of beach forming sediment and wood to the beaches adjacent to the river.  1939 aerial

By 1939,  the lagoon is disconnected from the river, forming what is now known as “Beach Lake”.  Beginning in the 1950’s large rip rap armor and concrete slabs were placed on the waterward side of the north boundary of Beach Lake in a failed attempt to ‘stop’ erosion.  However, with the dams still in place the beach forming sediment supply was still cut off, and the shoreline now covered with sediment deflecting armor. The shoreline continued to erode at a dramatic rate. The majority of the remnant Beach Lake armoring disappeared into the Strait of Juan de Fuca by 2006.

2011 aerial

By  2011 photo (above), Beach Lake was reduced to approximately 8 acres in size (a fraction of it’s historic scale).  The legacy of the armor that had been placed along the shoreline of Beach Lake to “protect” it from erosion had failed repeatedly and now instead  was littered throughout 2 acres of the intertidal shoreline-and was preventing beach forming sediment from settling.

2016 aerial

Whats Dam Removal Got to Do With It ?

The removal of the Elwha and Glines Canyon dams began in September 2011.   In the above 2015 photo, you can see the dramatic expansion of the Elwha River delta (~100 acres of new estuary habitat) and a yellow line indicating the location of the failed armoring that was littered throughout the historic Beach Lake nearshore.  Not only was this abandoned armor no longer serving a functional purpose, it was impairing habitat for salmon and forage fish, in addition to interfering with sediment and wood delivery and other natural beach forming processes.  It had all come full circle for this armor.  First, it was put there to prevent erosion that occurred because of the dams, but after 70 years, we learned that it was not successful at preventing erosion and it was actually interfering with the beach’s ability to mend itself once the removal of the dams delivered a 100-year pulse of sediment to this shoreline.

1950

pre project

Comparing the above 1950 and 2016 photos of this shoreline, you can see a dramatic shift from a sandy vegetated natural beach to a heavily altered beach that was littered with abandoned armor rock up to 6 feet in diameter.

In 2015, at the 9th Annual Elwha Nearshore Consortium workshop, Jamie Michel ( CWI nearshore biologist and project lead), initiated and led an interdisciplinary dialog that identified, for the first time, the direct relationship between shoreline armoring and the  persistent  erosion on this stretch of Elwha shoreline. And the first ecosystem restoration project of the Elwha nearshore was born. Coastal Watershed Institute approached the owner of a portion of this shoreline about their interest in a conservation sale of their property so that this stretch of shoreline could be restored to a natural beach and made available for the public to visit.  The landowner was very supportive of this concept as were the U.S. Fish and Wildlife Service (USFWS), Washington State Department of Ecology, Washington State Recreation and Conservation Office (RCO) and the Puget Sound Partnership.  Puget Sound Partnership  designated this project, named the Beach Lake Acquisition and Restoration Project, their #1 Habitat Priority in their 2016 Puget Sound Action Agenda which is available here.  In August of 2016, Coastal Watershed Institute purchased this property with funds from USFWS and RCO and immediately began the process of bringing this shoreline back to its full potential.  All of this happened just in time, as the beach forming sediments made available by dam removal will only be in this stretch of shoreline for  a short duration as the high wind and wave energy quickly moves sediment along this shoreline.  If we had waited any longer, we may not have had the chance to allow this beach to rebuild itself naturally.

IMG_20160813_054636496_HDR - Copy

Dawn, August 13, 2016, construction crews get to work removing armor from this beach.

IMG_20160813_083443

By 11 am the tide has come in and the beach work concludes for the day.

IMG_20160818_110927322 - Copy

Over the course of 6 days, approximately 3,000 cubic yards of abandoned armor and 100 cubic yards of concrete were removed from 2 acres of tidelands along 1/2 mile of shoreline so that this shoreline can repair itself.

post shoreline

Elwha Nearshore Rising

Within just one tidal cycle, natural processes were able to deliver beach forming material (sand and wood) to the upper portions of the beach and some areas of the beach grew upwards by almost 10 feet and outwards by 20 feet.  Pretty amazing how capable a natural system is of repairing itself once we get the impediments out of the way.

elwhanearshore20august2016wlogos copy

Above is a beautiful August 20, 2016 aerial photo of the expanding Elwha River delta and newly restored shoreline.  Notice how a lagoon system is beginning to re-establish to the left of the river’s mouth.  Who knows how this shoreline will continue to evolve now that another significant natural process impediment has been removed, but we are excited to watch and learn.

IMG_20160818_135713584

None of this work would have been possible without the partnership and support of numerous organizations.  The Lower Elwha Klallam Tribe was a key partner in the restoration. Bruch and Bruch Construction provided an outstanding team of equipment operators to get Phase I of the rock removal accomplished.  (Pictured above with the 3,000 cubic yard mountain of armor removed from the beach are (L-R Yonara Carillho of SWCA Environmental Consultants and George, Dale and Daryl of Bruch and Bruch Construction).  Additional partners essential to this project include: The Phillips Family, North Olympic Land Trust, John L Scott Real Estate, Washington Department of Natural Resources, Washington Department of Fish and Wildlife, Clallam County, U.S. Army Corps of Engineers, North Olympic Peninsula Lead Entity for Salmon Recovery, Coastal Geologic Services, Stratum Group, Patagonia (which is funding our ongoing monitoring), Olympic Peninsula Surfrider Foundation, Ecotrust, Olympic Peninsula Audubon Society, Hayes Family Foundation, Rose Foundation, The Seattle Foundation, Puget Soundkeeper Alliance and Lighthawk.

IMG_20160822_073849420

Anne Shaffer, lead scientist at CWI, Tara McBride, and WWU/PC student interns Sara Schoenmann and Sheri Washington are collecting critical baseline and post project monitoring data.

Photo: Tara, Sarah, and Sheri testing nearshore sampling techniques for Beach Lake monitoring.IMG_20160620_110055Together we  are working as quickly as possible to remove the existing buildings, re-vegetate the property and complete public access to this property, which we hope will be Summer 2017.  CWI will hold a public tour and workshop  Saturday morning, September 17 (9 am at the site) to celebrate the restoration unfolding at this amazing property and completion of Phase I of this restoration.  RSVP to join us for a sneak preview of this property before it is available for public access.